Proposed Schedule - Updated October 2023 |
|
Participant Involvement Program (PIP) initiated |
Q3 2022 |
First Public Open House | Q4 2022 |
Environmental assessment submitted to Alberta Environment and Parks (AEP) |
Q1 2023 |
Second Public Open House |
Q4 2023 |
Anticipated response from AEP |
Q4 2023 |
Submit to the Alberta Utilities Commission (AUC) |
Q4 2024 |
Anticipated approval from the AUC |
Q1 2025 |
Construction begins |
Q2 2026 |
Target Commercial Operations Date |
Q4 2028 |